All Milestones and Schedule:
Project Approved -- Completed
Project Manager assigned -- Completed
High-Level Project Milestones defined -- Completed
Microsoft Windows Server 2008 - Release 2: Micrsoft has confirmed ship date for October 22, 2009
In Development Environment resources will be required from the following groups:
- MSS Group
- UCC
- Enterprise Applications
- DBA
Milestone - Project Planning Meetings: Completed
- Session 1 -- Completed
- Session 2 -- Completed
- Session 3 -- Completed
Milestone - In Development Environment: Work in Progress
- Blade Chasses freed up, all former blades converted to virtual machines -- To be completed by November 20, 2009
- Windows 2008 image completed -- To be completed by November 25, 2009
- Development environment turned over to EntApps -- To be completed by November 25, 2009
Milestone - Move to Production Enviroment: Not Started
- Status provided on the availability of the production server provisioning -- To be completed by December 9, 2009
- Production server provisioning completed -- To be completed by December 16, 2009
- Software deployment completed -- To be completed by January 8, 2010
Milestone - Post Implementation Review: To be completed by January 16, 2010