All Milestones and Schedule:
I. Project Programming Complete -- Completed.
II. Budget Complete --- Completed.
III. Award of Cable Contractor -- Completed.
IV. Qwest CSO and approval-- Completed.
V. Construction - final completion -- Completed.
VI. Customer move in -- Completed.
VII. Change/Add Video Server Room cabinets and Fiber -- Completed.
VIII. Fiber to indoor practice field for FireAlarm -- Completed.
IX. Billing Complete -- TBD.
X. Project Closeout Complete -- TBD.