Weatherup Center - Indoor ASU Basketball Practice Facility


DSCF5510.JPG
Quick View
Summary: 

Provide voice-data and CATV services for the new facility located east of Rural Road and north of University Drive.

Start Date: 
March 1, 2008
Go Live: 
May 1, 2009
End Date: 
May 31, 2009
Current Milestone: 
Billing and Project Closeout -- July 30, 2009
Stage: 
Complete - In operation and supported by UTO.
People
Sponsor/Champion: 
Adrian Sannier, Vice President and University Technology Officer
Project Manager: 
Mike Brown
Contact for more information: 
carl.miller@asu.edu
Associate VP University Technology: 
Bob Nelson
University Technology Director: 
Craig Trimble
More Info
Source: 
Construction
Priority: 
Medium
Scope: 

Provide voice-data and CATV services for the new facility located east of Rural Road and north of University Drive.

All Milestones and Schedule: 

I. Project Programming Complete -- Completed.

II. Budget Complete --- Completed.

III. Award of Cable Contractor -- Completed.

IV. Qwest CSO and approval-- Completed.

V. Construction - final completion -- Completed.

VI. Customer move in -- Completed.

VII. Change/Add Video Server Room cabinets and Fiber  -- Completed.

VIII. Fiber to indoor practice field for FireAlarm --  Completed.

IX. Billing Complete --  TBD.

X. Project Closeout Complete --  TBD.

Deliverables: 

Provide voice-data and CATV services.

Risk & Threats: 

Go-Live date dependent upon construction schedule.