All Milestones and Schedule:
Build of Sybase ASE 15 environment - 6/17/2009 (COMPLETED)
Proof of Concept Migration from version 12.5 to version 15 - 6/21/20009 (COMPLETED)
Prototype New Enterprise1 Server - 6/24/2009 (COMPLETED)
Develop2 Test Migration (second iteration) - 7/15/2009
Tested Disaster Recover and live migration from one Zen Host to another - 7/21/2009 (COMPLETED - Thanks Jim Salverson)
Refinement of migration process for Develop2 and enterprise1 (build server start to finish for 2nd time) - 8/17/2009
Maintenance monitoring scripts converted and tested - 9/4/2009
Complete Licensing Conversion with Sybase for Platform Change - 9/4/2009 (COMPLETED 10/5/2009)
Convert PHP and Perl scripts used for backups, usage, etc.
Go-Live Migration Dates
develop2 - 11/09/2009
enterprise1 - 11/23/2009
Other Sybase servers - TBD