All Milestones and Schedule:
Project plan
Milestones
05/01/09 - Functional specification - Complete
05/14/09 - Scope/functional requirement overview with business owners - Complete
05/22/09 - Update / finalize functional spec - Complete
05/28/09- Create data model for survey data - Complete
07/1/09 - Development - Complete
07/7/09 - Unit and integration testing - Complete
07/13/09 - Migrate to Test - Complete
07/24/09 - Test Scripts Complete
08/28/09 - UAT Complete
09/09/09 - Migrate CRM Survey to Prod - Complete
09/09/09 - Migrate Reporting tables to Prod
10/01/09 - Migrate Survey reporting tables to Prod