All Milestones and Schedule:
Phase 1 - correct existing My Reports CTEL queries
07/02/2009 - revisit existing My Reports queries to all CTEL program to use TK20 for Summer students
07/24/2009 - complete changes to My Reports CTEL queries
9/14/2009 - SSO migratin to production. Waiting for CTEL to be ready to begin use.
12/01/2009 - planned complete automation of Tk20 My Reports queries and data send to Tk20
10/19/2009 ****Schedule change per Dr. Hurwitz - Single Sign-on delayed until start of Spring Term to allow college to prepare for SSO business changes and the addition of other campuses to Tk20 ********* Changes to Tk20 Queries will require project to be re-baselined.
12/01/2009 - Complete Requirements for Tk20 Data Pull Queries.
12/15/2009 - Updated Tk20 queries ready for CTEL review.
01/08/2010 - Automation of Tk20 Data Pull
January 2010 - single sign-on go-live