Timeclock Plus 6.0


Quick View
Summary: 

Installation of Timeclock Plus 6.0 into an enterprise environment for use across multiple departments at the university. This will provide an update to the Timeclock Plus 4.x installation used by UTO Sites and Classrooms.

Start Date: 
October 26, 2009
Go Live: 
November 30, 2009
End Date: 
December 7, 2009
Current Milestone: 
11/20/2009 - Document Environment Build/Config
Stage: 
On track
People
Sponsor/Champion: 
Adrian Sannier, Vice President and University Technology Officer
Project Manager: 
Debi Carl
Contact for more information: 
entapps@asu.edu
Associate VP University Technology: 
Max Davis-Johnson
University Technology Director: 
Shawn Bryan
More Info
Source: 
Internal
Department: 
UTO
Priority: 
Medium
Scope: 

1. Provide a multi-departmental timeclock solution for the university
2. Provide a means to support the timeclock solution remotely
3. Provide a web based clock in/out solution for hourly employees in the supported departments

All Milestones and Schedule: 
Task Subtask Assigned To Start Date Due By
Development
Server Build
  MSS 10/26/2009 10/30/2009
Development
Environment Install
       
  SQL Restore From Current Prod EntApps, SQL DBAs 11/2/2009 11/4/2009
  Firewall Openings EntApps, MSS 10/30/2009 11/4/2009
  Software install EntApps 11/4/2009 11/5/2009
  Database Upgrade EntApps(via Software) 11/4/2009 11/5/2009
  Publish Admin tool in MyApps EntApps 11/4/2009 11/5/2009
Development
Environement Config
  EntApps, Nathan 11/5/2009 11/6/2009
Document
Environment Build/Config
  EntApps 11/6/2009 11/12/2009
Development
Environment Testing
  Functional Users 11/6/2009 11/20/2009
Production
Server Build
  MSS 11/6/2009 11/23/2009
Production
Environment Install
       
  SQL Restore from Current Prod(?) EntApps, SQL DBAs 11/23/2009 11/24/2009
  Firewall Openings EntApps, MSS 11/19/2009 11/24/2009
  Software Install EntApps 11/24/2009 11/25/2009
  Database Upgrade EntApps(via Software) 11/24/2009 11/25/2009
  Publish Admin tool in MyApps EntApps 11/24/2009 11/25/2009
Turn
Over to Functional Users
  EntApps, Func Users 11/30/2009 12/7/2009
Deliverables: 

1. Fully Installed and configured Timeclock Plus 6.0 environment with Web Enabled Access
2. Remote administration and reporting capability for supervisors/managers

Syndicate content