All Milestones and Schedule:
• Define scope 5/30/2008 - complete
• Gather requirements 8/1/2008 - complete
• Develop implentation project plan 8/1/2008
(Development and implemention will be in value-added phases)
• Checkpoint
• V1.0 Develop, Test, Implement assign eval group & initial ratings 9/15/2008 - complete
• V2.0 Develop, Test, Implement acquire & eval documents 2/15/2009 - complete
• V3.0
Develop, Test, Implement assign addtn'l ratings 5/30/2009 - complete
(note: 4/22/09 additonal rating value needed due to change in Cronkite admission requirements)
Develop, Test, Implement auto admit 6/15/2009 - complete
Develop, Test, Implement dept rptg 6/25/2009 - complete
• Follow-up and close project 6/30/2009
.