All Milestones and Schedule:
I. Project Initiation/ Programming - Completed.
II. Award of Cable Contractor - Completed.
III. Site Survey - Ongoing Weekly.
IV. Gather Requirements - Completed.
V. Develop Proposal and Cost Estimate - Completed.
VI. Get Approval to Proceed, SLA signed - Completed.
VII. Receive and approve Qwest CSO - Completed.
VIII. Construction - Completed.
IX. Project sign-off of Cable Plant and TRs - Multiple Dates beginning 5-29-09 thru 8-14-09 -Completed.
X. Customer move in - July 15 ongoing through August 15th Student move-in - Completed.
XI. Project Closeout - 9/1/2009.
Billing - Completed.
Documentation - 11/4/2009 - Completed.