All Milestones and Schedule:
01-12-2009 - Kick Off meeting with HBE and UTO support for automation of Residental Life hall/wing information -- Completed
01-30-2009 - Design and schedule completed for Project. -- Completed
02-20-2009 - Test run of export processes. -- Completed
04-17-2009 - Implmenetation of process into production for the RMS export to ISAAC. -- In Progress; Working with TOPS on final process
06-17-2009 - Implementation of User data from PeopleSoft -- Dependent on IDWorks project
04-24-2009 - Implemenation of Import process on ISAAC -- Completed
04-30-2009 - Documentation, Ops and Care plans -- In Porgress