All Milestones and Schedule:
Check the vendors availability, and schedule staff availability before 6/8. - Completed - the vendor has scheduled us in to begin the upgrade on 6/8.
Milestone Dates:
Rplus - Milestone Dates for 9.x Upgrade
Outage from (7pm 06/07/2009 β 8am 06/09/2009)
06/07/2009 Servers Ready for CollegeBoard install (make sure CB will be able to access the servers)
06/07/2009 UTO DBA β 8.x Full Database backups including (DTS packages and Jobs)
06/07/2009 Block Users from accessing application (except: Delaney Dickerson & Ruben Minton & Maria Haugen)
06/08/2009 CollegeBoard 32-bit SQL2005 install scripts for upgrade on current Database server (RPLUSDB)
CollegeBoard .Net Application install
06/08/2009 UTO DBA β 9.x Full Database backups after upgrade is completed (but before testing starts)
06/08/2009 Servers Ready for Tier 1 user testing (Reuben , Delaney, Maria)
06/08/2009 or 06/09/2009 Disaster Recovery Final Decision (if applicable)
06/08/2009 CollegeBoard - Final Data Migration for 9.x
06/08/2009 UGA User interface rollout by USITS (only if issues, the web address is the same and itβs a .net web app)