Summary: 

Renovation of existing Department of Psychology space within Psychology , Psychology North, and Schwada Buildings. UTO will provide the infrastructure, voice and data services.

Start Date: 
January 19, 2009
Go Live: 
August 31, 2009
End Date: 
August 31, 2009
Current Milestone: 
Programming Space - 07/31/2009
Stage: 
Canceled - No UTO involvement.
People
Sponsor/Champion: 
Adrian Sannier, Vice President and University Technology Officer
Project Manager: 
Mike Brown
Contact for more information: 
craig.trimble@asu.edu
Associate VP University Technology: 
Bob Nelson
University Technology Director: 
Craig Trimble
More Info
Source: 
Construction
Priority: 
Medium
Scope: 

Renovation of existing Department of Psychology space within Psychology , Psychology North, and Schwada Buildings. UTO will provide the infrastructure, voice and data services.

All Milestones and Schedule: 

I. Project Initiation/ Programming - In progress

II. Project Funded - Awaiting Capital Programs Management

III. Award of Cable Contractor

IV. Site Survey

V. Gather Requirements

VI. Develop Proposal and Cost Estimate

VII. Get Approval to Proceed

VIII. Construction

IX. Customer move in

X. Project Closeout

Deliverables: 

Voice and data services.

Risk & Threats: 

Renovation dependant on construction funding.