Renovation of existing auditorium at the ASU Polytechnic Campus. Auditorium resides within the recently completed Polytechnic Academic Complex and will be updated to accomodate the ASU community regarding A/V, voice and data services.

Start Date: 
January 23, 2009
Go Live: 
November 30, 2009
End Date: 
December 18, 2009
Current Milestone: 
11/23/2009 - Network Installation -95% Completed.
Stage: 
On track
People
Sponsor/Champion: 
Adrian Sannier, Vice President and University Technology Officer
Project Manager: 
Mike Brown
Contact for more information: 
craig.trimble@asu.edu
Associate VP University Technology: 
Bob Nelson
University Technology Director: 
Craig Trimble
More Info
Source: 
Construction
Priority: 
Medium
Scope: 

Provide A/V, voice and data to Polytechnic Auditorium.

All Milestones and Schedule: 

I. Project Initiation/ Programming - Completed.

II. Award of Cable Contractor - Completed.

III. Site Survey - On going.

IV. Gather Requirements - awaiting matrix generation- 9-02-2009
- Completed

V. Develop Proposal and Cost Estimate - Completed.

VI. Get Approval to Proceed - Completed.

VII. Qwest CSO -10-30-2009 - Completed.

VIII. Construction - In Progress.

Copper/Fiber testing and certification - 11/4/2009 - Completed.

IX. Network Installation -  11-09-2009 thru 11/23/2009 - 95%-In Progress.

X. Blue Lights on Bakus Mall - 11/4/2009 - Completed.

XI. Customer Tentative move in- 11/26/2009.

XII. Project Closeout - 12/18/2009.

Deliverables: 

A/V, voice and data services.

Risk & Threats: 

Construction schedule is dependant on funding.

Syndicate content