All Milestones and Schedule:
I. Project Initiation/ Programming - Completed.
II. Award of Cable Contractor - Completed.
III. Site Survey - On going.
IV. Gather Requirements - awaiting matrix generation- 9-02-2009
- Completed
V. Develop Proposal and Cost Estimate - Completed.
VI. Get Approval to Proceed - Completed.
VII. Qwest CSO -10-30-2009 - Completed.
VIII. Construction - In Progress.
Copper/Fiber testing and certification - 11/4/2009 - Completed.
IX. Network Installation - 11-09-2009 thru 11/23/2009 - 95%-In Progress.
X. Blue Lights on Bakus Mall - 11/4/2009 - Completed.
XI. Customer Tentative move in- 11/26/2009.
XII. Project Closeout - 12/18/2009.