All Milestones and Schedule:
December 2009 – Exposure and Familiarity (build the demonstration environments, review release notes and begin technical training)
January 2010 – Planning with CMSC Confirmed (complete project plan and confirm CMSC planning for order of various environments)
February 2010 – Complete Strategy and Project Team (integrate Oracle upgrade into project plan, project testing needs and complete test plans, specify the integration tests and configuration needs, build IDP for CRM)
March 2010 – Technical and Functional Specification (Upgrade IDP for HRSA following U/F cycle, use IDP environment to specify retrofits needed to integration points, ASU enhancements and/or base-product, report errors to CMSC)
April 2010 – Complete Retrofits and Build Integration Testing Environment (apply changes to base product, prepare for development freeze by completing pending development, build test environments)
May 2010 – Test and Install in Production (complete acceptance testing and install in productin)
June 2010 – Lift Development freeze ( complete burn-in, problem resolution)
June 2010 – Upgrade database to 11g