Payroll Process Improvements - Combine On/Off Payroll Cycles


Quick View
Summary: 

Project to combine the bi-weekly,off-cycle payroll processing with the bi-weekly, on-cycle payroll processing.

Start Date: 
October 1, 2009
Go Live: 
November 30, 2009
Current Milestone: 
10/12/2009 - Financial Services would like to cancel this project at this time.
Stage: 
Canceled - No UTO involvement.
People
Sponsor/Champion: 
none
Project Manager: 
Myra Elias
Contact for more information: 
myra.elias@asu.edu
Associate VP University Technology: 
Max Davis-Johnson
University Technology Director: 
Clara Adams
More Info
Source: 
Internal
Department: 
Business and Finance
Priority: 
none
Scope: 
  • CRM Case #306131 - Combining Off- and On-Cycle Payroll Processing