Payroll Paycheck new vendor


paycheck clip art.gif
Quick View
Summary: 

This project will move checking printing and web based W-2 printing from Ceridian to ADP.

Start Date: 
November 18, 2008
Go Live: 
July 31, 2009
End Date: 
June 30, 2009
Current Milestone: 
7/28/2009 - golive for ADP
Stage: 
Complete - In operation and supported by UTO.
People
Sponsor/Champion: 
Morgan Olsen, Executive Vice President and Chief Financial Officer
Project Manager: 
Clara Adams
Associate VP University Technology: 
John Rome
University Technology Director: 
Tina Thorstenson
More Info
Source: 
Executive
Department: 
Business and Finance
Priority: 
High
Scope: 
  1. Print Services Implementation
  2. Information Exchange
  3. Design Warrant Mock Up and obtain internal approval
  4. Digitize Process (signature image)
  5. ADP Program Initialization and Set ups
  6. interface Programming and Set ups
  7. Format and Edit Testing
  8. Formatting Corrections
  9. Payroll Testing
  10. MICR Line Testing
  11. Parallel Test

Case associated:

  • CRM Case #314773
  • CRM Case #378646 - ADP Print Services
  • All Milestones and Schedule: 

    Print Services Implementation - kickoff meeting

     Jan 2009

    Information Exchange:

    • ADP provide forms, record layouts and documentation
    • Distribute WEB server eligibilty form
    • Supply ADP with Web Server Eligibility Form, Authrorized Signature Form, Banking MICR specs for all accounts and Logo image

     Jan - Mar 2009

    Completed

    Design Warrant Mock Up and obtain internal approval

    • Design Warrant Mock Up and obtain internal approval
    • Complete Interface Analysis
    • Finalize check distribution requirements
    • Complete Web server set-ups

     Mar - May 2009

    Completed

    Digitize Process (signature image)

    • Submit Image Transmittal Request to laser imagaing for signature and logo
    • Digitized files returned and loaded to MF

     Feb - Mar 2009

    Completed

    ADP Program Initialization and Set ups

    • Submit Custom Programming Set up request to CP group
    • Devleop and initialize custom print program
    • Create Batch Master with client banking information

     Feb - May 2009

    Completed

    Interface Programming and Set ups

    • Develop Custom Interface
    • Load interface on client system
    • Complete interface setups/configurations on client system

     Mar - May 2009

    In process

    Format and Edit Testing

    • Submit test file to ADP for visual inspection/testing
    • Run file through ADP, print output, and review
    • Write up errors with suggestions
    • Make modification to interface and deliver revised interface to client

     May - June 2009

    In process

    Formatting Corrections

    • Web Server Communications test
    • Submit test file to ADP for visual inspection/testing
    • Run file through ADP, print output, and review
    • Write up errors with suggestions
    • Comprehensive review by client
    • Make modification to interface and deliver revised interface to client

     May- June2009

    In process

    Payroll Testing

    • Present test file to ADP for testing (250 minimum items)
    • Present corresponding label file for visual inspection/testing
    • Run file through ADP, print output, and review
    • Write up errors with suggestions
    • Comprehensive review by client

     June 2009

    In process

    MICR Line Testing

    • Present ADP a test file with 50 checks for MICR line approval
    • ADP to print, review and forward samples to client
    • Client to approve MICR coding
    • Notify ADP when bank approves

     May - June 2009

    In process

    Parallel Test

    • Present parallel test file and corresponding labels for visual inspection/testing
    • Run file through ADP, print output, and review
    • Write up errors with suggestions
    • Comprehensive review by client
     June 2009

    Go Live 

    • Provide ADP with a 12 month processing file schedule
    • ADP put in scheduling queue
    • Sign off on Production File Authorization
    • Sign off on Transmission File Authorization
    • Complete New Start Form for Production
    • Verify job ticket and shipping instructions
    • ADP moves program to Production
    • Client moves program to Production
    June 2009

    Production

    • Transmit live payroll #1 and confirmation sheet
    • Process file, confirm totals, print, split, and prepare to ship
    June 2009

    Transition Client to Client Account Manager

    • Hand off meeting
    July 2009
    Deliverables: 

    New Vendor pay checks

    New interface file to Vendor

    Syndicate content