Migration of ETS (Engineering Technical Services) / SOD (Server on Demand) Environment to ISTB1 Data Center


Quick View
Summary: 

The purpose of this project is to move ETS/SOD servers from Fulton Center to the ISTB1 Data Center creating an enterprise level of service. 

The following benefits will be realized:

  • Reduce network complexity
  • Reduce dependency - currently there are two locations
  • Simplify troubleshooting
  • Increase performance - spindles will "run" faster
  • Increase power protection with 3 hours of backup power available
  • No change in equipment
Start Date: 
January 13, 2009
Go Live: 
August 7, 2009
End Date: 
September 11, 2009
Current Milestone: 
9/11/2009 -- Final documentation (As-Built) for network and server configuration .
Stage: 
Complete - In operation and supported by UTO.
People
Sponsor/Champion: 
Adrian Sannier, Vice President and University Technology Officer
Project Manager: 
Mike Brown
Contact for more information: 
Terry.Hinton@asu.edu
Associate VP University Technology: 
Bob Nelson
University Technology Director: 
Terry Hinton
More Info
Source: 
Internal
Priority: 
Medium
Scope: 

Coordinate the relocation of ETS / SOD servers from Fulton Center to ISTB1. This will require installing infrastructure in ISTB1 to include cable tray, networking hardware and power.

All Milestones and Schedule: 

Discovery phase:

  • Determine network infrastructure -- Completed.
  • Determine storage needs - Completed.
  • Document all existing connections to include VLAN and IP addresses (As-Is) -- Completed.
  • Determine location and cage requirement in ISTB1 -- Completed.
  • Detail various options for solution with pricing to install power, racks, switches, fiber, etc. -- Completed.
  • Evaluate options for solution -- Completed.
  • Select option -- Completed.
  • Develop budget -- Completed.
  • Approve budget  -- Completed.

Design Phase:

  • Design/Engineer solution -- Completed.
  • Document (To-Be) as designed -- Completed.
  • Approve Design -- Completed.

Installation phase:

  • Order equipment -- Completed.
  • Receive equipment -- Completed.
  • Install equipment in Data Center --Completed.
  • Phase 1: Move Poly Chassis/Blades/VMs --Completed.
  • Phase 2: Move ETS Chassis/Blades/VMs from Fulton Center -- Completed.
  • Phase 3: Move LIB Chassis/Blades/VMs  --Completed.
  • Phase 4: SOD Team to advise what VLANs need to move from GWC to ISTB1 -- Completed.
  • Phase 5: Move VLAN Subnets  from GWC to ISTB1. -- 8/07/2009 -- Completed.
  • Final documentation (As-Built) for network and server configuration -- 9/11/2009
  • Post Implementation Review -- 9/11/2009

 

 

Deliverables: 

Provide an enterprise level solution in the ISTB1 Data Center for ETS / SOD server racks.

Risk & Threats: 

No funding for project has been identified.