Medical Education Building / Health Science and Education Building Project


Const1.JPG
Quick View
Summary: 

Provide voice and data services for the Medical Education Building / Health Science and Education Building located in Phoenix.

Funding is in place - start dates have not been set.

 

Start Date: 
June 13, 2008
Current Milestone: 
11//30/2009 - Project Initiation. Design phase
Stage: 
On track
People
Sponsor/Champion: 
Adrian Sannier, Vice President and University Technology Officer
Project Manager: 
Mike Brown
Contact for more information: 
john.totlis@asu.edu
Associate VP University Technology: 
Bob Nelson
University Technology Director: 
Craig Trimble
More Info
Source: 
Construction
Priority: 
Medium
Scope: 

Provide voice and data services for the Medical Education Building / Health Sciences and Education Building located in Phoenix.

All Milestones and Schedule: 

I. Project Initiation/ Programming - Awaiting further requirements from project - 50% Complete.

II. Award of Cable Contractor

III. Site Survey

IV. Gather Requirements

V. Develop Proposal and Cost Estimate

VI. Get Approval to Proceed

VII. Construction

VIII. Customer move in -- Assigned to Qwest Managed Services - Revised Tentative opening - 5/15/2012

IX. Project Closeout

Deliverables: 

Voice and data services for the Medical Education Building / Health Science and Education Building located in Phoenix.

Risk & Threats: 

Go-Live date dependent upon construction schedule.

Syndicate content