Provide voice and data services for the Interdisciplinary Science and Technology Building IV (ISTB).

This project is in the programming stage and budget is being worked.

 

Start Date: 
March 1, 2008
Go Live: 
October 1, 2010
End Date: 
October 15, 2010
Current Milestone: 
Awaiting budget & project approval.
Stage: 
On hold
People
Sponsor/Champion: 
Adrian Sannier, Vice President and University Technology Officer
Project Manager: 
Mike Brown
Contact for more information: 
Carl.Miller@asu.edu
Associate VP University Technology: 
Bob Nelson
University Technology Director: 
Craig Trimble
More Info
Source: 
Construction
Priority: 
Medium
Scope: 

Provide voice and data services for the Interdisciplinary Science and Technology Building IV (ISTB).

 

All Milestones and Schedule: 

I. Project Initiation/ Programming -Complete

II. Award of Cable Contractor

III. Site Survey

IV. Gather Requirements

V. Develop Proposal and Cost Estimate - 7/31/2009 Complete

VI. Get Approval to Proceed

VII. Construction

VIII. Customer move in

IX. Project Closeout

Deliverables: 

Provide voice,video and data services.

Risk & Threats: 

Go-Live date dependent upon construction schedule.