All Milestones and Schedule:
Define detail project plan, timeline, resources - Complete
Sample CSV file to be used for Development - Complete
Analyze file, verify data is valid for import, and provide mapping data to developer. Complete
Develop spec for data import - 2/20/09 - Complete
Inititate Development of import script - 2/20/09 - Complete
Test (DEV) import script using sample CSV file data - 4/03/09 - Complete
Import data from CSV file to Installed Product Tables - 5/8/09
Customer sign off - 5/08/09