All Milestones and Schedule:
* Create replication of SA tables to PSREP, ASU schema, 8/1/2009, Angie - COMPLETE
* Gray out file upload option on SAM, 7/22/2009, Lily - COMPLETE
* SQL Update to remove file upload from supp apps, 7/28/2009, Angie - COMPLETE
* Alter db structure and stored procedures in Sybase Dev and QA, 8/1/2009, Roger - COMPLETE
* Alter web app to read from PS SA tables - if no connection get most current eff date/eff seq from PSREP, 8/21/2009, Josh - COMPLETE
* Manage eff date and eff seq on Program of Interest table, 8/21/2009, Josh - COMPLETE
* Ensure no web app connections to Graduate Program Code table, 8/21/2009, Josh - COMPLETE
* Create preview function end point, 9/4/2009, Josh - COMPLETE
* Alter LOR app to dynamically pull questions and text, 8/21/2009, Bill - COMPLETE
* Validate that XML Publisher process works with new LOR format, 8/21/2009, Bill - COMPLETE
* Create test plan and coordinate functional testing, 8/21/2009, Angie - COMPLETE
* Build sql to update apps in progress, 8/28/2009, Josh - COMPLETE
* Alter AgentLoader logic for creating app tag, 9/25/2009, Josh - COMPLETE
* Alter app load process, if applicable, 9/4/2009, Lily - COMPLPETE
* Identify departments that have modified supp app since conversion to SAM in 2008, 9/4/2009, Roger - COMPLETE
* Integrate SAM with preview function end point, 9/4/2009, Lily/Josh - COMPLETE
* Complete QA Testing/Provide signoff, 9/25/2009, Angie - COMPLETE
* Migrate db changes, web app, LOR, AgentLoader, SAM changes and PS app load changes, 10/01/2009, Josh/Lily/Bill - COMPLETE
* Remove permissions from old supp app tool in Gportal, 10/01/2009, Roger - COMPLETE