Graduate College Web Site Improvements and Move to Drupal 6


Quick View
Summary: 

Develop a new template for the Graduate College web site, update content and move web site to Drupal 6 environment.

Start Date: 
August 3, 2009
Go Live: 
January 16, 2010
End Date: 
January 16, 2010
Current Milestone: 
12/30/2009 - Integrating and refining new content into web site
Stage: 
Rebaselined
People
Sponsor/Champion: 
none
Project Manager: 
Roger Lurie
Contact for more information: 
roger.lurie@asu.edu
More Info
Source: 
Internal
Priority: 
High
Scope: 

Re-design Graduate College web site, update content and move to Drupal 6

All Milestones and Schedule: 

* Obtain consensus and approval on design of new web site, 8/29/2009 - COMPLETE
* Build template and enable Javascript, 10/2/2009, Bill - COMPLETE
* Obtain feedback from Provost Communications Group and GC Senior Staff, 10/30/2009, Bill/Roger - COMPLETE
* Refine templates, 10/30/2009, Bill - COMPLETE
* Move all custom mods to Drupal 6, 11/20/2009, Bill - COMPLETE
* Complete editorial review of content, 12/18/2009 - IN PROGRESS
* Post updated content to new web site, 12/30/2009, Bill - IN PROGRESS
* Final review of web site, 01/09/2010, Web Group
* Launch new web site, 01/16/2010, Bill