All Milestones and Schedule:
* Create detailed specifications with mock-ups, 10/12/2009, Angie - COMPLETE
* Review with users and reach consensus on design and requirements, 10/19/2009, Angie - COMPLETE
* Acquire Tomcat project space, 10/19/2009, Josh - COMPLETE
* Alter LOR Monitor BPEL Process and/or existing Java process if applicable, 11/20/2009, Josh - COMPLETE
* Develop Java front facing app and SOA/BPEL components, 11/25/2009, Josh - IN PROGRESS
* Prepare test plan, 11/25/2009, Angie - COMPLETE
* Complete QA Testing and user sign-off, 12/04/2009, Angie
* Enable link(s) in My ASU, 12/11/2009, My ASU Team
* Migrate app into production, 12/11/2009, Josh