All Milestones and Schedule:
March 5 - Complete business specification document, Roger
April 1 - Obtain My ASU approval for Request Change and View My I-20/DS-2019, Roger
April 1 - Create detailed specs for I-20 Mod, Admin Interface for GC Change Form, Nelnet reconciliation and database schema, Angie
April 1 - Build detailed request to My ASU team, Angie
April 1 - Build SQL for user interface, Angie
May 8 - Complete composite app development, Bill
May 15 - Complete development of BPEL's, Bill/Josh
June 8 - Complete integration with Nelnet Black Box, Bill/Josh
June 9 - Complete development on admin interface, Lily
June 26 - Complete integrated testing, Angie
June 26 - Communicate with academic units with 4 week notice, Mike
July 15 - Complete development and testing of Nelnet reconciliation, Lily
July 30 - Complete automated template to students with change form details, Jon
July 30 - Coordinate enablement in My ASU, Roger
August 3 - Go live