What is the Faculty Activity Report?
The Faculty Activity Report (FAR) is an online tool used to track the accomplishments of ASU faculty for evaluation and informational purposes.

What is being done in FAR Version 2?
The product that is currently in production at the site http://far.asu.edu is powered by a 3rd party provider. Far Version 2 will not be powered by a 3rd party provider in preparation for the 2009 evaluation cycle. Version 2 will include only services and capabilities available prior to 2008. 

Why are you moving away from the 3rd party provider?
The UTO met with several colleges to find out what changes ASU could make to increase the usability of FAR to our customers.  Nearly every meeting resulted in a single fact: ASU faculty found the older version more usable than the tool deployed for the 2008 cycle.

Who are you talking with over the course of this project?
We are speaking with a number of college representatives, Deans, Chairs, and faculty who have expressed interest in the success of this product.  We formed a focus group dedicated to the successful deployment of a product that can be expanded in future revisions tomeet the needs of their groups.

What can I expect during this migration?
There will be a data entry freeze as of December 19th, 2008 at 5:00 PM, which will be in effect until the replacement application is launched on January 5th, 2009.  This new application will include the data that was entered for prior years, and the respective evaluations.  Your data will be read only once the freeze is in place, but not editable.

What is this Uncategorized Data? 

As part of the project to move from Digital Measures FAR (DM) back to our original FAR system, we are converting data from DM back into our original system.  Since the data fields from Digital Measures do not always map cleanly to the fields in the replacement system (the FAR available prior to 2008), we've had to make some assumptions for the location of some data.  With the help of several faculty and staff from the many colleges, we're confident that these assumptions will be correct.  In some cases, there will be no logical place to move DM data.  In these cases this uncategorized data is being migrated and stored in a location where faculty who have entered the data into DM can still access it to copy and paste it into the appropriate FAR fields.

What are the plans for FAR and the Directory?

With the short amount of time provided to bring this application back, there are some "post production" tasks that the UTO will be completing in the first quarter of 2009.  The ASU Directory will be among those tasks.  The directory will include any information provided prior to the freeze, but that information will not be updated with new FAR information until the 3rd week in February. 

Where was my data migrated to?

 

  1. Personal Contact Information and Profile Information will no longer be entered into FAR, but will be made available through the Uncategorized Data pages to copy and paste into the Directory.
  2. Education will also no longer be entered into FAR, but will be made available through the Uncategorized Data pages should you wish to copy and paste them into Directory.
  3. Book Sections have been migrated to Book Chapters
  4. Books Reviewed have been migrated to Books Reviewed
  5. Books Authored have been migrated to Books Authored
  6. Invited Commentaries have been migrated to Commentaries
  7. Community Service has been migrated to Community Service
  8. Conference Proceedings has been migrated to Conference Proceedings
  9. Performing Art has been migrated to Creative Activities
  10. Play writes have been migrated to Creative Activities
  11. Visual Art has been migrated to Creative Activites
  12. Encyclopedia Articles have been migrated to Encyclopedia Articles
  13. Patents have been migrated to Patents
  14. Awards and Honors will be migrated to Honors
  15. Law Review Articles will be entered into Law Review Articles
  16. Mentoring will be migrated into Mentoring
  17. Professional Service have been migrated to Professional service
  18. Abstracts have been migrated to either Refereed or Non Refereed Articles as they were noted in the record
  19. Journal Articles have been migrated to either Refereed or Non Refereed Articles as they were noted in the record
  20. Magazine Articles have been migrated to either Refereed or Non Refereed Articles as they were noted in the record
  21. Newspaper Articles have been migrated to either Refereed or Non Refereed Articles as they were noted in the record
  22. Technical and Research Reports have been migrated to either Refereed or Non Refereed Articles as they were noted in the record
  23. Monetary Awards have been migrated to Service Monetary Awards
  24. Short Stories and Poetry have been migrated to Short Stories/Poetry/Novels/and Creative Non-Fiction
  25. Special Issues have been migrated to Special Issues
  26. Collaborative Activities have been migrated to Collaborative Activities
  27. Presentations have been migrated to Scholarly Conference Presentations/Exhibitions/Colloquia 
  28. University Service has been migrated to University Service
As we stated above, in some cases there was no logical place for the record to be migrated to.  In these cases the records are being displayed in the Uncategorized Data pages so that the faculty might migrate the data to the appropriate places.  The following Digital Measures categories were not migrated to a category in FAR, and are being stored in the Uncategorized Data pages.
  1. Broadcast Media
  2. Creative Writing
  3. Education
  4. Government Publications
  5. Instructors Manuals
  6. Interviews
  7. Licensures and Certifications
  8. Manuscripts
  9. Measurement Instruments
  10. Media Art
  11. New Course Materials
  12. Newsletters
  13. Non-Credit Instruction
  14. Notification of Consulting
  15. Pamphlets
  16. Positions Held
  17. Professional Development
  18. Professional Memberships
  19. Published Projects
  20. Research in Progress
  21. Software
  22. Study Guides
  23. Web Publications
  24. Websites
  25. Works in Progress
  26. Working Papers

 

Who can I contact to find out more information on FAR?
For support or access to the current system,  please email far@asu.edu.  Please include your full name, your ASURITE UserID, and your college or department name.

For more information on the FAR 2.0 project or future revisions, please email the FAR Project Manager, Noel Lindner, at noel@asu.edu.

 

JANUARY 5TH UPDATE - 

Technical difficulties have prevented the deployment of the new web interface for FAR.  The application will launch on January 7th, 2009.  

 

February 27th Update - 

The completion of the Directory updates has been delayed by 2 weeks.  This update is due to be released the week of March  8th, 2009.

 

March 11th Update - 

The remaining tasks, including Directory and My Profile functinality have been been rescheduled due to resource and time constraints. Please note these changes in the Project Schedule and Milestones.

 

April 10th Update - 

Development tasks have been completed, but the web services for the data links between FAR and My profile/Directory are delayed by 1.5 weeks.  These will be available by April  21st.

 

Start Date: 
August 1, 2008
Go Live: 
January 5, 2009
End Date: 
May 1, 2009
Current Milestone: 
4/22/2009 - Migrate Directory and My Profile web services
Stage: 
Recently Released - Completed in last 3 months.
People
Sponsor/Champion: 
Elizabeth D. Capaldi, Executive Vice President and University Provost
Project Manager: 
Noel Lindner
Contact for more information: 
noel@asu.edu
Associate VP University Technology: 
Max Davis-Johnson
University Technology Director: 
Leah Lommel
More Info
Source: 
Executive
Priority: 
High
Scope: 
  • Identify code for original FAR application
  • Provide Gap Analysis
  • Development for only critical pieces found in Gap Analysis
  • Data Mapping from DM database to ASU Database
  • Develop migration scripts
  • Migrate stored data
  • Create Training Materials
  • Provide external testing opportunities
  • Create reporting mechanism through EPM
  • Recreate links to Directory (real time)
  • Research and possibly create a delegate function for this application
All Milestones and Schedule: 
  • 10/24/2008 - Data Mapping Complete, Gap Analysis complete, code base in dev
  • 12/5/2008 - Migration Iteration 1
  • 12/12/2008 - Migration Iteration 2
  • 12/15/2008 - Begin Faculty Focus Group Testing in Dev
  • 12/19/2008 - Data Freeze
  • 12/31/2008 - WebDav migration
  • 1/5/2009 - Launch
  • 1/5/2009 - Documentation Complete
  • 1/15/2009 - Start My Reports migration
  • 2/13/2009 - My Reports available to Deans
    • My reports is available.
  • 2/27/2009 - Directory links enabled
    • This has been delayed and will be due the week of March 8th.

Rebaseline Remaining Tasks - March 11, 2009

  • 3/25/2009 - Engineering Report Sample
  • 4/10/2009 - Development Tasks completed-  this WAS POSTPONED DUE TO TESTING ISSUES
    • Add/Edit User Functionality Improvements
    • Web Services for My Profile and Directory
  • 4/17/2009- FAR Ops/Care plan completed
  • 4/24/2009 - Scope for FAR 2.5 completed
Deliverables: 
  • Restoration of original FAR system
  • Migration of data entered into DM, as well as historical data
  • Training materials
  • End user assistance
Risk & Threats: 
  • Data migration will delay the project
    • Categories within Digital Measures do not line up to those in FAR.
    • Digital Measures more fields in each category, which will need to be mapped and placed in their appropriate locations
    • These migrations will require testing from a focus group regularly
  • Evaluation year can effect the way a publication is displayed in one database vs. another
    • Digital Measures has 1 record for every year a publication is sited in a FAR, where as classic FAR has 1 database entry per year the publication was sited.
  • The system will have no customizations that were not originally built into the system.
    • We will be able to take in suggestions, but no changes that aren't critical to the functioning product will be added to the scope.
  • Gap Analysis of the evaluation process for all the colleges may require a large amount of development time
  • The application is written in a programing language that is not technically supported by the UTO, this will need to be addressed at some point, if not in this project.
  • The Directory links and web services will need to be recreated