All Milestones and Schedule:
-PeopleSoft development complete in DEV by 7/24/2009
-Migration of PeopleSoft development to SATST completed by 7/27/2009
-Testing in SATST completed by 7/28/2009
-Migration request to SAPRD submitted by 5pm 7/28/2009 for regular migration to PRD on 7/29/2009 -or- by 9am 7/30/2009 as emergency migration before system wide migration freeze.
Development of Blackboard link (building block)
-Initial development complete by 7/28/2009
-Testing complete by 7/30/2009
-Migration to production night of 7/31/2009
Requirements and project plan complete - 7/20/2009