ERE (Employer Related Expenditures) Flat Rate Proposal


umb clip art.png
Quick View
Summary: 

This project will change the Employer Related Expenditures calculated by Payroll from an actual basis to a flat rate basis. We currently interface the actual rate (PS delivered/calculated as part of the regular payroll processing) to Advantage and this will continue without changes. The new calculation will also be interfaced to advantage.

Start Date: 
July 9, 2008
Go Live: 
October 30, 2009
End Date: 
November 30, 2009
Current Milestone: 
10/23/09 - Testing Complete - Ready for Production
Stage: 
Recently Released - Completed in last 3 months.
People
Sponsor/Champion: 
Morgan Olsen, Executive Vice President and Chief Financial Officer
Project Manager: 
Myra Elias
Contact for more information: 
myra.elias@asu.edu
Associate VP University Technology: 
John Rome
University Technology Director: 
Clara Adams
More Info
Source: 
Executive
Department: 
Business and Finance
Priority: 
High
Scope: 

The HURON Consulting Group was brought in by the Office of Budget and Planning to make a recommendation for a flat ERE (Employer Related Expenditure) rate. They were to analyze our data and propose their findings. Once approved, they would submit a plan to the Government for approval of the ERE rate(s). Then become an integral part of the implementation project.

Associated Case

  • CRM Case #375199 -ERE Encumbrances - have been moved to another project
  • CRM Case #407627 -ERE Encumbrances for RA/TA Tuition Remission
  • All Milestones and Schedule: 

    Fringe Benefit Rate Implementation Approach

      Step 1: Calculate FY08 Rate (July - September 2008)

    • Obtain actual FY08 fringe benefit costs
    • Determine all programs that should be included
    • Develop categories
    • Obtain FY08 salaries by category
    • Develop allocation methodology and cost model
    • Calculate FY08 fringe benefit rate from each category
      Step 2: Determine Impact to Institution (October 2008)

    • Review results of FY08 fringe benefit rate
    • Determine cost recovery impact
    • Review draft fringe benefit rate with University management
    • Finalize methodology and cost model
    • Contact DHHS (Department of Health and Human Services) and request approval
      Step 3: Calculate FY10 Rate (November - December 2008)

    • Obtain FY10 projected finge benefit costs
    • Obtain FY10 projected salaries by category
    • Calculate FY10 fringe benefit rate
      Step 4: Scope Definition/Specifications to HRIS (March - May 2009)

    • Define requirements
    • Document the Functional Specifications
    • Document the Technical Specifications
      Step 5: Implement and Update Systems (April - May 2009)

    • Submit fringe benefit rate proposal to DHHS (Department of Health and Human Services)
    • Document rate calculation processes and assumptions for the cost model
    • Revise payroll system to apply fringe benefit rate
    • Create new accounts/object codes in Advantage to track costs and allocations
      Step 6: Test Systems (May - June 2009)

    • Fringe benefit rate calculated fro each category
    • Application of calculated fringe benefit rate for employee categories
    • Fringe benefit costs are recorded accurately
      Step 7: Rollout Fringe Rate (June 2009)

    • Negotiate a fringe benefit rate with DHHS (Department of Health and Human Services)
    • Implement fringe benefit rate for FY10
    • File an amended Disclosure Statement

    Scope Discussions

  • 7/10/2008 - The Office of Budget and Planning host Huron Consulting Group for a pre kick-off meeting with ASU
  • July to Decmeber 2008 - Data compilation for determination of rates.
  • 9/3/2008 - Project Status meeting with HURON
  • 1/20/2009 - ERE scope discussion
  • 1/26/2009 - Further ERE scope discussion
  • 2/4/2009 - Tuition Remission scope discussion
  • 2/17/2009 - Payroll setup discussion
  • 2/18/2009 - Review Earnings used for determining fringe benefit rate and Continued payroll setup discussions
  • 2/19/2009 - Tuition Remission discussion
  • 2/27/2009 - Tuition Remission Specification discussion
  • 3/3/2009 - ERE Payroll setup discussions
  • 3/5/2009 - Update Deston with information regarding rates
  • 3/13/2009 - Payroll set up pros/cons/feasibility
  • 4/2/2009 - Prepare Functional Spec for development
  • 4/15/2009 - Finalized Spec requirements
  • 4/21 to 7/14/2009 - Standing touch point meetings - Complete
  • 4/20/09 - Refine ERE functional spec
  • 4/27/09 - ERE UAT - complete
  • 05/04/09 - Create RA/TA functional spec - complete
  • 05/11-29/09 - Refine RA/TA functional spec - complete
  • 06/01/09 - RA/TA specs complete - complete
  • 06/22/09 - CMT communication for ERE - complete
  • 06/22/09 - RA/TA coding complete - move to STG for testing (use prior pay periods for testing) - complete
  • 06/22-8/15/09 - RA/TA UAT testing (FALL 2009, SPRING 2010 and SUM 2010)- In progress
  • 06/26/09 - Communication about ERE changes with departments (Financial Services) - Complete -
  • 06/26/09 - Query/Report Changes (Financial Services) - Complete
  • 09/02/09 - Provide a draft Business Process Guide for ERE - draft to Financial Services, complete
  • 07/02/09 - ERE project in production - Complete
  • 08/31/09 - Provide a draft Business Process Guide for RA/TA- not complete
  • 07/15/09 - CMT communication for RA/TA - Complete
  • 09/01/09 - Communication about RA/TA changes with departments (Financial Services) - not complete -
  • 09/07/09 - RA/TA project in production - not complete -
  • 09/01/09 - Turn over support of projects to support team - not complete
  • Deliverables: 

    Create a process to calculate ERE based on a flat rate

    Create a process to calculate RA/TA tuition remission for Fall, Spring and Summer

    Create a process to interface the ERE flat rate amounts and RA/TA from Peoplesoft to Advantage

    Create a Business Process Guide for ERE

    Create a Business Process Guide for RA/TA for each semester Fall, Spring and Summer

    Query and report changes.