Enterprise SharePoint


Quick View
Summary: 

SharePoint has a lot of traction within the ASU environment for collaboration, basic work-flow, and project management.  The current SharePoint environment needs to address a few items to make it more supportable and dynamic.

This project is to sure up, design and document delegation roles.

Start Date: 
October 27, 2008
Go Live: 
January 9, 2009
End Date: 
January 18, 2009
Current Milestone: 
Project completed.
Stage: 
Recently Released - Completed in last 3 months.
People
Sponsor/Champion: 
Adrian Sannier, Vice President and University Technology Officer
Project Manager: 
Sharan Johnson
Contact for more information: 
robin.manke@asu.edu
Associate VP University Technology: 
Bob Nelson
University Technology Director: 
Robin Manke-Cassidy
More Info
Source: 
Internal
Scope: 
  • Bring the standards of the SharePoint environment up to enterprise standards.
  • Add the additional 2 web servers into the farm.
  • Patch and update to the latest versions.
  • Document the granular management roles.
  • Installation of the Enterprise SharePoint key.
All Milestones and Schedule: 
  • Complete the sync between SharePoit Dev and production for all sites.  This will allow for testing of future patches and upgrades as well as site owner development. (6 hours)
  • Test and then deploy to production the enterprise upgrade. (6 hours)
  • Test and then deploy to production the "infrastructure patch". (12 hours)
  • Add two IIS servers for web server redundancy. (16 hours)
  • Install the i-filter for one note notebook files. (4 hours)
  • Review logs and resovle minor server erros and issues (8 hours)

All enterprise upgrades will occur on Saturday evening after all the backups to the production system have completed. 