All Milestones and Schedule:
Research vendors -- To be completed by November 13, 2009
In-House Demonstration (by vendors) -- To be completed by December 11, 2009
Vendor Selection -- To be completed by December 31, 2009
Pilot -- To be completed by February 28, 2010
Presentation to UTC -- To be completed by April 30, 2010
Implementation -- To be completed by June 30, 2010
Live in Production -- June 30, 2010
Project Closeout -- To be completed by July 9, 2010