All Milestones and Schedule:
I. Project Initiation/ Programming - awaiting end user(funding for integrator & relocation to facility)
II. Award of Cable Contractor - Completed.
III. Site Survey -Completed.
IV. Gather Requirements, Build Matrix - 10/09/2009 - Completed.
V. Develop Proposal and Cost Estimate - 10/30/2009 - Completed.
VI. Get Approval to Proceed - 11/6/2009 -Completed.
VII. Construction-11/19/2009
VIII. First Customer group tentative move in--11/20/2009.
IX Second Customer group tentative move in--12/18/2009.
X. Project Closeout--12/30/2009.