Effort Reporting - Close Period 3


Quick View
Summary: 

Address all production issues as follows in order to allow Period 3 to be closed:

A12 configuration issue
Cost share dashboard presenting incorrect data - duplicate data because of projects translation to accounts
Basic search replacement with Advanced search reconfiged with limited defaults

Start Date: 
February 4, 2009
Go Live: 
April 17, 2009
End Date: 
April 20, 2009
Current Milestone: 
Complete
Stage: 
Complete - In operation and supported by UTO.
People
Sponsor/Champion: 
R.F. Rick Shangraw, Vice President of Research and Economic Affairs
Project Manager: 
Robin Manke-Cassidy
Associate VP University Technology: 
John Rome
University Technology Director: 
Tina Thorstenson
More Info
Source: 
Executive
Priority: 
High
Scope: 

Address all production issues as follows in order to allow Period 3 to be closed.

Deliverables: 
  • A12 configuration issue -> Migrated, waiting on functional approval.
  • Cost share dashboard presenting incorrect data - duplicate data because of projects translation to accounts -> COMPLETE
  • Basic search replacement with Advanced search reconfiged with limited defaults -> COMPLETE