eAdvisor: On/Off Track Reporting v3.2


EeAdvisor On-Off Batch.jpg
Quick View
Summary: 

Modifications and improvements to the existing processes of on/off track reporting. See scope for more details.

Start Date: 
January 7, 2009
Go Live: 
April 2, 2009
End Date: 
April 10, 2009
Current Milestone: 
04/02/09 - Go Live
Stage: 
Complete - In operation and supported by UTO.
People
Sponsor/Champion: 
Elizabeth D. Capaldi, Executive Vice President and University Provost
Project Manager: 
Barbara Sowden
Contact for more information: 
Barbara.Sowden@asu.edu
Associate VP University Technology: 
Max Davis-Johnson
University Technology Director: 
Leah Lommel
More Info
Source: 
Executive
Priority: 
High
Scope: 
  • Checkbox / Override with no expiration date at a critical requirement level. Include a unique field (ASU_PSNAME) to carry the override forward when a change to the sub requirement ID occurs
  • Display check/X combo image when a requirement is taken in a later track term than required. This image does not change.
  • Add CT09 students to critical tracking group
  • Evaluate student based on Plan/Sub Plan level
All Milestones and Schedule: 

Functional Specs - 02/6/09
1st Round Development - 03/06/09
Testing - 03/13/09
2nd Round Development - 03/27/09
Migrate to TST & Final Testing - 3/30/09
Migrate to PRD - 04/01/09
Go Live - 04/02/09