All Milestones and Schedule:
Create Test environment to validate the upgrade path: May 26 – June 15
· Validate ability of MyApps to support ASURITE servers: June 8 - June 12
· Create the test environment in ASURITE: May 29 - June 12
Obtain three VM’s for Application, Web and Citrix servers
Move the agent server from the current test environment
Obtain space on the enterprise MSSQL Dev server to host the AX databases
Obtain iSCSI Netapp space for the image store
· Install Documentum v 6.0 in the new test environment: June 8 – June 12
Take a copy of the production databases from ENTSQL1 and move to the Dev SQL Servers to allow for data upgrade
Take a copy of the production image store from ENTAPP1 and move to the Test Image store
Create/Modify account support within the application to allow for ASURITE access
· Validate the test environment with Grad College, ORSPA and USI to identify any issues: June 15 – July 17
Install Documentum v 6.0 into the production environment: June 17 – July 24
· Create Production environment in ASURITE: June 17 – June 30
Obtain three VM’s for Application,Web servers and citrix server
Move the agent server from the current production environment
Obtain space on the enterprise MSSQL Prod server to host the AX databases
Obtain iSCSI Netapp space for production image store
Identify the Citrix servers in production that will host the application
· Install Documentum v 6.0 in the production environment: June 30 – July 24
Take a copy of the production databases from ENTSQL1 and move to the Prod SQL Servers to allow for data upgrade
Take a copy of the production image store from ENTAPP1 and move to the Prod Image store
Create/Modify account support within the application to allow for ASURITE access
· Validate the test environment with Grad College, ORSPA and USI to identify any issues: July 24 – July 29