Dashboard - UGA 1.2


Picture 15.png
Quick View
Summary: 

The UGA Dashboard has been in production a while. Feedback and a need to get consensus on the reporting that is brings back has prompted this re-tooling of the board. We will conduct further outreach and redesign accordingly.

Start Date: 
September 14, 2009
Go Live: 
November 27, 2009
End Date: 
December 4, 2009
Current Milestone: 
11/30 Resolve all issues with the Admission Fact Table that provides the data to the dashbaord
Stage: 
Missed milestone
People
Sponsor/Champion: 
none
Project Manager: 
Matt Sheppard
Associate VP University Technology: 
John Rome
More Info
Source: 
Executive
Department: 
UTO
Department: 
University Student Initiatives
Priority: 
High
All Milestones and Schedule: 

10/08/09-Deliverable Mock-ups out for review