Quick View
Summary: 

Provide infrastructure and support to continue the Blackboard version 9 pilot. Use of Blackboard nine will be restricted to faculty that used the fall 2009 Blackboard 9 instance. Training and exploration activities will continue to prepare for the implementation of the enterprise wide Blackboard Nine.

The infrastructure for Bb Nine will be locally hosted at ASU.

Start Date: 
November 2, 2009
Go Live: 
January 8, 2010
End Date: 
May 26, 2010
Current Milestone: 
11/16/2009 - Specify hardware for small scale Blackboard installation at ASU
Stage: 
Proposed - Project Initiation/Intake Assessment
People
Sponsor/Champion: 
Adrian Sannier, Vice President and University Technology Officer
Project Manager: 
Steve Knuteson
Contact for more information: 
Katherine.Ranes@asu.edu
Associate VP University Technology: 
Max Davis-Johnson
University Technology Director: 
Shawn Bryan
More Info
Source: 
none
Department: 
UTO
Priority: 
High
Scope: 

Establish small scale Bb 9 installation

  • Purchase/install hardware
  • Install Bb9
  • Install integration with ASU Single Sign-on (ASU Web Auth)
  • Install integration with ASU Course Management infrastructure

Configure Bb9 with settings based on Fall Bb9 pilot

Transfer content/users from Hosted Blackboard installation

Prepare transition from Bb Managed Hosting to Bb9 at ASU

Give access to instructors and students

Support those using Bb9 throughout the Spring semester

Position for merging into the Bb9 Enterprise at the end of Spring