Lissa Kelley
|
Position Lockdown
- HRIS Modification Request Form
- Scope Definition - 7/15/2009
- Functional Specifications - 8/03
- Technical Review 7/23/2009
- Development -09/1 to 9/11
- User Acceptance testing - 9/30 to 10/9
- Test Plan Documentation - 10/14
- Document Business Process Guide- 10/14
- Transition to Support Team - 11/30
|
In Prroduction 10/14/2009 |
|
Lissa Kelley
|
Min/Max Salary for Job Codes
- HRIS Modification Request Form
- Scope Definition - 7/15/2009
- Functional Specifications - 7/15/2009
- Technical Review 7/23/2009
- Development -09/1 to 10/2
- User Acceptance testing - 10/5 to 10/9
- Test Plan Documentation 10/28
- Document Business Process Guide - 10/28
- Transition to Support Team - 11/30
|
eHire in production 10/21
MSS/Job in production 11/4
|
|
Loretta Coates
Lissa Kelley
|
MSS Termination Updates
- HRIS Modification Request Form
- Scope Definition
- Functional Specifications
- Technical Review
- Development 10/12 - 10/16
- User Acceptance testing 10/19 to 10/23
- Test Plan Documentation 11/4
- Document Business Process Guide - 11/4
- Transition to Support Team - 11/30
|
To be in production 11/4 or 11/11
|
|
Lissa Kelly
|
Renewal submitter
- HRIS Modification Request Form
- Scope Definition
- Functional Specifications
- Technical Review
- Development 8/21 - 10/16
- User Acceptance testing - 10/16
- Test Plan Documentation - 10/21
- Document Business Process Guide -10/21
- Transition to Support Team - 11/30
|
In production 10/21 |