A.E. England Building Project (ASU Downtown Campus)


A.E.England.jpg
Quick View
Summary: 

This is a remodel of an existing building and is currently in tenant improvement and final design stage.
Provide ASU voice-data services within ASU assigned space and wireless 802.11 throughout the A.E. England Building (DPC). City of Phoenix Parks and Recreation will manage and operate the entire building. ASU will have nominal space within the new building. Schedule is dependant upon City of Phoenix and awaiting others for construction schedule.

Start Date: 
July 1, 2008
Go Live: 
August 31, 2009
End Date: 
August 31, 2009
Current Milestone: 
8/31/2009 -- Project Close and Review .
Stage: 
Complete - In operation and supported by UTO.
People
Sponsor/Champion: 
Adrian Sannier, Vice President and University Technology Officer
Project Manager: 
Mike Brown
Contact for more information: 
craig.trimble@asu.edu
Associate VP University Technology: 
Bob Nelson
University Technology Director: 
Craig Trimble
More Info
Source: 
Construction
Priority: 
Medium
Scope: 

Provide voice-data services for the A.E. England Building (DPC).

All Milestones and Schedule: 

I. Project Initiation/ Programming – Complete.

II. Award of Cable Contractor - Complete.

III. Site Survey - ongoing weekly.

IV. Gather Requirements -Complete.

V. Develop Proposal and Cost Estimate -Complete.

VI. Get Approval to Proceed & Qwest CSO -Complete.

VII. Construction - Complete.

VIII. Move-in tentative -- 8/17/2009- Complete..

IX. Project Close and Review -- 8/31/2009.

Deliverables: 

Voice and data services for the A.E. England Building (DPC).

Risk & Threats: 

Go-Live date dependent upon construction schedule.