eAdvisor: My Major Maps v1.0

Quick View
Summary: 

Move My Major Map prototype into production for Sun Devil Tracking students to use. The web application will inform students of what critical courses, GPAs and milestones need to be completed to be successful in the major. Students will have the option to see how the courses they have taken apply to other majors if interested in changing majors. Advisors will be able to view the same information as students. Additional notes will be added to give students complete information.

Start Date: 
September 15, 2008
Go Live: 
November 3, 2008
End Date: 
November 15, 2008
Current Milestone: 
10/31/08- GO LIVE
Stage: 
Complete - In operation and supported by UTO.
People
Sponsor/Champion: 
Elizabeth D. Capaldi, Executive Vice President and University Provost
Project Manager: 
Barbara Sowden
Contact for more information: 
Barbara.Sowden@asu.edu
Associate VP University Technology: 
Max Davis-Johnson
University Technology Director: 
Leah Lommel
More Info
Source: 
Executive
Priority: 
High
Scope: 
  • Give advisor the ability to click a “View as Student”, and see the students Major Map. Use same functionality as My ASU project.
  • Migrate application to QA and PRD
  • Add Catalog Year to student data at the top
  • Have First Year Composition requirement link to the course catalog information.
  • Modify the layout/text style on the student info at the top of the page. This data all blends together. Personalized data should look different that title text.
  • Add plan and track term notes in from PS tables
  • Add “View Unmet Requirements” audit link
  • Apply student feedback gathered in observation sessions
All Milestones and Schedule: 
Milestones Target Date
Create Project Plan Sep 15
1st Round of Development Oct 3
Testing & Revise Mockups Oct 8
2nd Round of Development Oct 15
Testing & Modifications Oct 22
Final round of development Oct 29
Final Testing Oct 30
Final Lead Customer Sign off Oct 30
Go Live Nov 3
Deliverables: 
  • My Major Map application in production
  • Inter-connected links between My ASU and Course Catalog
Risk & Threats: 

Notes will be stored in Plan Extension data in PeopleSoft. A modification to AD0042 is required in order for this to be completed. There is a freeze to PRD until mid Oct. There is potential risk that we will not meet deadlines if environments are not available as planned in the tools upgrade schedule. There is also potential risk if we do not have a PeopleSoft developer to complete the work.

Residency Calculation v1.0

Quick View
Summary: 

Create a component that both undergraduate and graduate admissions applications can use to calculate residency. The component uses inputs from the invoking application to determine if the student is a resident or needs further manual review. A new web application will be created so staff can complete and display what the student's residency would be based on how the questions were answered.

Start Date: 
August 18, 2009
Go Live: 
December 30, 2009
End Date: 
December 30, 2009
Current Milestone: 
11/15/09 - Residency Office Testing
Stage: 
Missed milestone
People
Sponsor/Champion: 
James Rund, Vice President of University Student Initiatives
Project Manager: 
Barbara Sowden
Contact for more information: 
Barbara.Sowden@asu.edu
Associate VP University Technology: 
John Rome
University Technology Director: 
Leah Lommel
More Info
Source: 
Executive
Priority: 
High
Scope: 
  • Create an API to be used by undergraduate and graduate applications
  • Create technical documentation on how to intergrate the API into the undergraduate and graduate applications
  • Follow residency flow diagram to create API
  • Create an external web page that can be completed and display what the residency would be based on how the questions were answered.
Deliverables: 
  • An application programming interface (API) to provide to support requests made by the undergraduate and graduate admissions application
  • Technical documenation which details how to integrate into admissions applications

AVP's and UTO Labs

The project form has a new field under "People" called "Associate VP University Technology." It has been added to assign a project to an AVP. A "view" to see assignment has been created at http://utolabs.asu.edu/avp

Common Computing Image Expansion

Quick View
Summary: 

As the common image project gains exposure more departments at ASU are becoming interested in using the image and the services provided by the image development and deployment team. While the number of licenses and image staff has not grown, the requests for the service has greatly expanded and the university does not currently adhere to hardware standards.

Goal of the project: The goal of this project is to develop a sound plan that will allow any ASU entity to use the image. The plan will have to include the expansion of current software licenses; imaging hardware; a set of hardware standards; and a process to partner with the various university technical teams to share resources during the development and deployment.

Stage: 
Staging - Draft version. Will not show up in a search. Viewed only by URL or PM menu.
People
Sponsor/Champion: 
none
Project Manager: 
No Project Manager
Associate VP University Technology: 
Sarah Hughes
More Info
Source: 
none
Priority: 
none

ASU PD: Expand implementation of New World Systems to other campuses

ASU PD Picture.jpg
Quick View
Summary: 

The ASU Police Department uses New World Systems to manage its records and dispatch.  Currently the system is installed in police department at Tempe.  The access to the system needs to be extended to ASU Police Deparment offices at ASU Polytechnic, ASU West and ASU Downtown Phoenix Campus with appropriate network design to comply with system security requirements.

Start Date: 
September 8, 2008
Go Live: 
February 20, 2009
End Date: 
February 27, 2009
Current Milestone: 
04/14/2009 - Confirm Production use successful
Stage: 
Complete - In operation and supported by UTO.
People
Project Manager: 
Katherine Ranes
Contact for more information: 
Katherine.Ranes@asu.edu
Associate VP University Technology: 
Bob Nelson
University Technology Director: 
Katherine Ranes
More Info
Source: 
Executive
Priority: 
Medium
Scope: 

Deploy New World Systems at the Downtown Phoenix Campus, ASU West Campus and ASU Polytechnic Campus.

  • Develop network design
  • Implement network changes
  • Deploy application at ASU Downtown Phoenix Campus
  • Deploy application at ASU West Campus
  • Deploy application at ASU Polytechnic Campus
  • Complete training of distributed staff
  • Prepare support plan for distributed staff workstations

 

All Milestones and Schedule: 
  • Develop network design (complete) - Citrix approach determined for Recording
  • Confirm workplan with ASU PD and others  10/8/08 - Complete
  • Install Servers for Citrix Deployment in ASU PD  10/8/08 - defer
  • Install Microsoft SQL Server Express for the Datastore on Server 2  10/13/08 - defer 
  • Implement Citrix Presentation server 10/13/08 - defer
  • Deploy application in Citrix environment 10/13/08 - defer
  • Confirm users access to Citrix application 10/15/08 - defer
  • Design Mobile Module - Field Reporting access 10/20/08
  • Test connectivity 10/28/08 - firewall solution not viable
  • Change to network requires funding
  • Funding for network changes identified 11/07/2008 - complete
  • Configure device for Poly - Complete
  • Install device at Poly - 12/10/08
  • Test Poly after network change - 12/12/08
  • Order devices for DPC and West - complete
  • Configure DPC device - 12/15/08
  • Install at DPC Campus - 12/20/08
  • Test DPC 1/9/09
  • Install new jacks as West Campus - 01/05/2009
  • Install device at West 01/13/09
  • Test West connectivity 1/15/09
  • Move computers to new locations at West 01/20/09
  • Test West after computer moves and network change - 01/25/09
  • Testing at distributed locations complete 01/28/09
  • Complete training of distributed staff 01/28/09
  • Prepare support plan for distributed staff workstations 01/28/09
  • Customer target 11/01/08 Rebaseline to 02/01/09

    Deliverables: 

    Deployed system with appropriate security and support.

    Student Records/Registrar Processing Improvements - Spring 2009

    Quick View
    Summary: 

    Improvements and enhancements needed to address current needs and processing changes.

    Start Date: 
    January 1, 2009
    Go Live: 
    August 10, 2009
    End Date: 
    August 17, 2009
    Current Milestone: 
    08/06/2009 - Mods Final & moved to PRD
    Stage: 
    Complete - In operation and supported by UTO.
    People
    Sponsor/Champion: 
    James Rund, Vice President of University Student Initiatives
    Project Manager: 
    Bonnie Stoneking
    Contact for more information: 
    stoneking@asu.edu
    Associate VP University Technology: 
    John Rome
    University Technology Director: 
    Leah Lommel
    More Info
    Source: 
    Executive
    Priority: 
    Medium
    Scope: 

    Process improvements needed by the end of Spring 2009. Many of these items address process changes from past improvements. See Deliverables for details...

    All Milestones and Schedule: 

    3/6/2009 - Development underway
    4/3/2009 - Testing Round 1
    4/10/2009 - Testing Round 2,
    5/13/2009 - Testing Round 3, release to mods
    07/08/2009 - Mods Final & moved to PRD

    Deliverables: 

    Testing
    * Milestone QBU; CRM 362215; needed May

    On hold
    * Print legend on back of student transcript (2Q or summer improvements);CRM 377390
    * Grade Change Transcript Note; SR0156 spec written;
    * Grade Changes after Degree is awarded; SR0159 spec written;
    * Grade Change Detail Button; SR0157 spec written; on hold
    * Changing ‘W’ audit grades; SR0155 spec written; on hold

    Done
    * Move Design Pre Plans students to Design Plans; done 3/4
    * Move Film-Exploratory students (BAFLMPRE to FAFPRBA); done 3/17
    * Display Student's campus on Student Service Center; CRM 347031; done 03/19
    * Changes to the Academic Status Report; CRM 356607; done 3/24/09
    * Display Student's Milestone on Student Service Center; SR0167; CRM 362223; done 4/23
    * Batch Transcripts for Athletes; SR0160; CRM 318999; done 5/6
    * Default Class Credits; spec written; CRM 376862; needed June; done 6/24

    Moved to Academic Structure project
    * Sync Acad Org tree to PSREP; mod AI0024; CRM 335452; TST

    SQL 2005 Cluster Infrastructure for HIPAA environment

    Quick View
    Summary: 

    Create a MS SQL 2005 clustered environment for the HIPAA Windows environment. New applications moving into the environment require MS SQL 2005. This is a prerequesite for the following projects:

    • Psychology Department: Move HIPAA Application to HIPAA Environment - Version 1.0
    • CLAS TIMS application (SHS) migration to UTO HIPAA environment
    Current Milestone: 
    AVP approval and prioritization.
    Stage: 
    Canceled - No UTO involvement.
    People
    Sponsor/Champion: 
    Adrian Sannier, Vice President and University Technology Officer
    Project Manager: 
    Sharan Johnson
    Contact for more information: 
    robin.manke@asu.edu
    Associate VP University Technology: 
    John Rome
    More Info
    Source: 
    Internal
    Priority: 
    Needs Prioritization
    Scope: 

    Installation of an MS SQL 2005 cluster in the HIPAA environment.

    All Milestones and Schedule: 
    • Identify hardware and software requirements - operations:systems -> September 5, 2008
    • Order hardware and software - operations
    • Racking of hardware - operations:facilities & operations:Ops
    • Installation of Hardware - operatios:systems
    • Installation of SQL software - operations:systems & EDS
    • Configuration of SQL environment - EDS
    • Configuration of Backups for data base and for system. - operations:systems & EDS
    • Documentation of environment - operations:systems & EDS
    • Ops & Care plans - operations:systems & EDS
    Deliverables: 

    Enterprise ready MS SQL 2005 cluster for HIPAA environment.

    Risk & Threats: 
    • Projects listed in the summary are dependent on this environment.  Without this environment those projects can not be completed.

    ASU Online v2.5

    webredesign.jpg
    Quick View
    Summary: 

    Seemlessly integrate Innovation Ads processes into the ASU student web experience, including: recruiting students; assisting them through the application, admission, and enrollment process; in some cases advising students; and monitoring and assisting students through to graduation.

    Start Date: 
    September 8, 2008
    Go Live: 
    April 17, 2009
    End Date: 
    May 1, 2009
    Current Milestone: 
    5/1/2009 - burn in.... Ops & Care Plans
    Stage: 
    Complete - In operation and supported by UTO.
    People
    Sponsor/Champion: 
    Elizabeth D. Capaldi, Executive Vice President and University Provost
    Project Manager: 
    Bonnie Stoneking
    Contact for more information: 
    stoneking@asu.edu
    Associate VP University Technology: 
    Max Davis-Johnson
    University Technology Director: 
    Leah Lommel
    More Info
    Source: 
    Executive
    Priority: 
    High
    Scope: 

    See Project site for the project plan and meeting notes.

    All Milestones and Schedule: 

    02/27/2009 - testing block online students from taking in person classes CRM 347084, SR0163
    re-baselined - dev time took longer
    03/06/2009 - testing complete block online students from taking in person classes
    03/13/2009 - sign off by Registrar Office
    03/18/2009 - in Production

    ------
    Re-Baselined - ran into problems during testing
    04/03/2009 - sign off by Registrar Office
    04/07/2009 - in Production
    -----
    Re-Baselined - problems during testing
    4/10/2009 - sign off by Registrar Office
    4/15/2009 - in Production

    Risk & Threats: 

    excess development time and competing priorities for developer

    Dashboard - Effort Reporting v.1.1 - Project Centric Principal Investigator

    effort reporting.png
    Quick View
    Summary: 

    Project directors may have responsibility for employees that cross departmental boundaries. Develop a report (dashboard)that lists employees by project (Coeus award) with responsible DEA, essentially an effort reporting certification to do list. The objective is to provide a research project's principal investigator with an easy to use front end that has the ability to deep link into PeopleSoft to perform effort reporting certification.

    CRM Reference: 291734

    Current Milestone: 
    05/15/09 Scope Update Approval
    Stage: 
    Canceled - No UTO involvement.
    People
    Sponsor/Champion: 
    R.F. Rick Shangraw, Vice President of Research and Economic Affairs
    Project Manager: 
    Matt Sheppard
    Associate VP University Technology: 
    Max Davis-Johnson
    University Technology Director: 
    Tina Thorstenson
    More Info
    Source: 
    Executive
    Priority: 
    Lower

    Dashboard - eAdvisor v2.0

    Quick View
    Summary: 

    The eAdvisor dashboard receives its data from the Advisor Tracking Tool data structures. Changes during the Advisor Tracking Tool version 3.0 project resulted in significant data structure changes. The goal of Dashboard eAdvisor v2.0 is to rewrite queries to pull the data from the new table structures.

    Start Date: 
    September 25, 2008
    Go Live: 
    October 23, 2008
    End Date: 
    October 30, 2008
    Current Milestone: 
    Have updated data in PRD - 10/10/08
    Stage: 
    Complete - In operation and supported by UTO.
    People
    Sponsor/Champion: 
    Elizabeth D. Capaldi, Executive Vice President and University Provost
    Project Manager: 
    Barbara Sowden
    Contact for more information: 
    Barbara.Sowden@asu.edu
    Associate VP University Technology: 
    Max Davis-Johnson
    University Technology Director: 
    Leah Lommel
    More Info
    Source: 
    Executive
    Priority: 
    High
    Scope: 
    1. Get new table structures in EPM
    2. Update dashboard queries to use new data structures
    3. Improve speed for how long it takes data to return
    4. Give access to academic advisors
    5. Minor text modifications
    Deliverables: 
    • Updated data in eAdvisor dashboard
    • Access to academic advisors