| 18 Month Information Technology Security Audit Response | On track | December 31, 2009 | 11/25/2009 - Documentation Approved | Noel Lindner |
| AMS Online Course Eval Integration with Webauth | On track | October 21, 2009 | 12/30/2009 - Turnover complete | Leema Lallmamode |
| ASU Blogs & Wikis Transition | On track | | 12/01/09 Implement wiki hosting partner for new wikis | Adrian Teo |
| ASU Data Center: Server on Demand Informational Web Site | On track | December 15, 2009 | 10/30/2009 - Spec completed | Leema Lallmamode |
| ASU Data Center: Storage on Demand Informational Web Site | On track | December 15, 2009 | 10/30/2009 - Spec completed | Leema Lallmamode |
| ASU General Security Training - 18 Month Audit Requirement | On track | November 30, 2009 | 11/20/2009 - Training Materials Approved | Noel Lindner |
| ASU Maps - Maintenance | On track | November 13, 2009 | 11/20/09 - Feedback to UAO | Lissa Gladden |
| ASU Search | On track | December 31, 2009 | 11/20/09 - Fix broken Help Center keymatches | Lissa Gladden |
| ASU Web Developer Security Training - 18 Month Audit Requirement | On track | November 27, 2009 | 11/30/09 - Release Blackboard course to Web Developers | Barbara Sowden |
| ASU Web Infrastructure Scanning - 18 Month Audit Requirement | On track | December 7, 2009 | 11/25/2009 - Documenation Approved | Noel Lindner |
| ASU West Campus Converged Voice-Data Network Upgrade- Phase1 | On track | June 30, 2010 | 12/11/2009 - Upgrade active CAT3 Ethernet cabling to CAT6. -In Progress. | Mike Brown |
| ASU/Pearson Fall 2009 Implementation | On track | August 28, 2009 | 12/08/2009 - debrief/plan for Spring 2010 classes | Bonnie Stoneking |
| Audit Requirements - Disaster Recovery Exercise - October 2009 | On track | November 6, 2009 | 11/13/2009 Disaster Recovery Site Shutdown | Debbie Brown |
| Automated Payroll Graduate Tuition Waiver Processing | On track | November 17, 2009 | 11/20/2009 - First deduction on payroll warrant (one pay period date late) - adjusted over 4 pay periods instead of 5 | Clara Adams |
| Barrett, The ASU Honors College | On track | July 15, 2009 | December 7th, move all of the Barrett Honors Advisors from the local client to the Citrix client. | Jon Finley |
| Campus Health - NextGen Upgrade to version 5.5 | On track | December 17, 2009 | 11/30/2009 - Building out the presentation servers on VM machines | Debi Carl |
| Campus Health - Scheduware EPM Installation | On track | December 4, 2009 | 11/20/2009 - Addressing issues identified during the ARB review | Debi Carl |
| Cellular Distributed Antenna System (DAS) -Barrett Residence Hall - Phase I | On track | July 31, 2010 | 11/20/2009 - Finish Proposal and send to Verizon/ATT - Assigned NextG . | Mike Brown |
| CEM V.2 - Course Enrollment Manager Improvements | On track | December 15, 2009 | 11/20/2009 - Initial Development Complete | Gillian Bailey |
| Change management system v2.0 | On track | November 1, 2009 | 10/30/2009 - Review remaining requests | Leema Lallmamode |
| CLAS : Main CLAS website maintenence | On track | | 11/17/09 - buildout CLAS boxes for MyASU | Adrian Teo |
| CLAS : Research Resource Catalog | On track | October 26, 2009 | 11/19/2009 - Complete manager function | Jeffrey Beeman |
| CLAS Advisor Online Scheduling System | On track | March 2, 2009 | 12/15/2009 - Complete Engine Tables | Gillian Bailey |
| CLAS: Leroy Eyring Center for Solid State Science - Website redesign | On track | | 11/19/09 - complete first comps, initial template | Adrian Teo |
| CRM Request Required Date for CRM case | On track | December 11, 2009 | 12/11/09 - Migrated to Corda 3 (prod) | Frank Montoya |
| Dashboard - eAdvisor v 2.5 | On track | December 18, 2009 | Development of sql for changes to the Sun Devil Tracking KPI - 11/23/2009 | Kristian Borkman |
| Dashboard for PeopleSoft Security and Advantage Access Information | On track | | 11/30/2009 Dashboard design complete | Susan Moore |
| Data Project for Research Reporting | On track | December 24, 2009 | Nov. 30, 2009: Review of data by principals. In progress. | Rick Bolin |
| E2 Campus Enhancement | On track | December 4, 2009 | 11/12/2009: Test SEED Functionality | Nancy Biro |
| eAdvisor: Course Catalog v 3.0 | On track | February 26, 2010 | 11/30/09 - Prioritize scope items | Barbara Sowden |
| eAdvisor: Prerequisite Review/Drop of Classes V2.5 | On track | November 30, 2009 | 11/24/09 - Dashboard Testing/Modifications | Barbara Sowden |
| eAdvisor: Program Search v3.5 | On track | November 30, 2009 | 11/30/09 - Next Round of Development/Testing | Barbara Sowden |
| eCustoms Payment Screening Application (Tri-University): Phase 2 - U of A and NAU Implementation | On track | December 30, 2009 | December 31, 2009 Automate processing of files. | Sharan Johnson |
| Effort Reporting - Administrative Guide Edits | On track | December 30, 2009 | 11/20/09 - Finalize edits to ER003 admin guide | Frank Montoya |
| Effort Reporting Committed Module Tuning / Calc and display VUCS and OTC project lines | On track | | 11/05/09 - Commited Module Technical Review | Frank Montoya |
| ei8ht Relocation to the Cronkite-ei8ht Building at DPC Campus | On track | January 1, 2010 | 11/19/2009 - Construction. | Mike Brown |
| Electronic Thesis and Dissertation (ETD) Version 1.0 | On track | January 15, 2010 | 12/04/2009 - Coordinate ARB approval pending details from UMI/ProQuest | Roger Lurie |
| Evaluate Options for Replacement of NetID | On track | | Nov 30 2009 Make decision concerning acceptance of Qwest's proposal | Greg Wilson |
| EZappt | On track | August 7, 2009 | 12/30/2009 - Turnover complete | Leema Lallmamode |
| Faculty Productivity - Grading Improvements V 2.0 | On track | November 13, 2009 | Compile documentation necessary to turn over application to Ops and Care - December 1, 2009 | Kristian Borkman |
| Financial Audit: Payroll Process Improvement - Time and Leave Reporting Performance Improvement | On track | November 30, 2009 | 11/30/2009 - Continued Data Clean up for TL by payroll - waiting on department feedback | Myra Elias |
| fsaAtlas - Upgrade to Version 7.5 | On track | November 10, 2009 | 11/25/2009 - Waiting on hotfix release | Debi Carl |
| Graduate Applicant Self Service Form for Online Recommendations | On track | December 11, 2009 | 11/25/2009 - Develop Java front facing app | Roger Lurie |
| Graduate Student Format Advisement Tool | On track | November 23, 2009 | 11/23/2009 - QA testing and usability testing with group of graduate students | Roger Lurie |
| Graduation Automation v2 | On track | December 17, 2009 | 11/25/2009 - PS development complete | Bonnie Stoneking |
| High School Electronic Transcript Intake v2 | On track | May 31, 2010 | 12/15/09 Define points of influence and promotion plan | Marilyn Shipp |
| Human Resource Process Improvement - Outsource Verification of Employment and Electronic I-9 Verification | On track | January 29, 2010 | 11/16/2009 - move to development for coding | Clara Adams |
| Implement profiles in EDNA | On track | | 12/31/2009 Map affiliation to profiles/services | Susan Moore |
| Install U.direct 3rd Party Software | On track | December 4, 2009 | 11/30/09 - Install Security Application | Barbara Sowden |
| Instructor Edit/Selection | On track | February 1, 2010 | 01-15-2010 - MyASU mods complete | Gillian Bailey |
| Integrated Voice Contact Center -Phase I | On track | June 30, 2010 | 12/31/2009 - Determine which ASU Call Center groups are impacting the scheduling of upgrades to the Avaya Switch platform | Mike Brown |
| LeRoy Eyring: Billing Automation v2.0 | On track | December 11, 2009 | 11/30/09 - Development | Barbara Sowden |
| MarchingOrder v2.0 | On track | December 11, 2009 | 12/04/2009 - send address information and Honors thesis data | Bonnie Stoneking |
| Medical Education Building / Health Science and Education Building Project | On track | | 11//30/2009 - Project Initiation. Design phase | Mike Brown |
| My ASU - Housing v.2 | On track | November 30, 2009 | 11/30/09 - Migrate to PROD | Lissa Gladden |
| Network Access Streamlining/Simplification - Network & Security Administrative Interface | On track | July 31, 2009 | 12/18/2009 Technical documentation completed; Communication and demo to ASU TAG completed. | Sharan Johnson |
| New Concepts in Course Enrollment Management Reporting | On track | December 18, 2009 | Develop MyReports Query - December 7, 2009 | Kristian Borkman |
| Nursing Student Advancement | On track | September 17, 2010 | 02/01/10 - 1st Round Development | Barbara Sowden |
| Payroll 2009 W2/1042S Year End Processing | On track | January 30, 2009 | 11/30/09 - Refine 2009 YE Task List, Begin W2 and W4 testing, Begin W2 interface mod | Myra Elias |
| Polytechnic Aravaipa Auditorium Renovation | On track | November 30, 2009 | 11/23/2009 - Network Installation -95% Completed. | Mike Brown |
| Processing Transfer and Job Function Changes | On track | | 11/20/2009 Identify criteria to identify employees on administrative leave who need access removed | Susan Moore |
| Role based access to Super Report for Principal Investigators | On track | December 15, 2009 | 11/20/09 - Extract from Coeus automated | Tasleema Lallmamode |
| SCLIntra Application - Phase 1 Mail Services Implementation | On track | December 31, 2009 | December 11, 2009 -- Conform receipt of VPN Edge Card(s). | Sharan Johnson |
| STAR Budgeting System - Upgrade to version 7 | On track | November 20, 2009 | 11/20/2009 - Development Install | Debi Carl |
| Streamlining MACS, eAdvisor, Graduation | On track | | 12/11 - Meeting with Letters & Sciences, University College and Public Programs to discuss streamlined advising | Atalaya Wilder |
| Student Distribution List Improvements | On track | December 1, 2009 | 11/25/2009 - Documentation Complete | Noel Lindner |
| Student Profile | On track | December 18, 2009 | November 27, 2009 - Phase one testing completed. | Sharan Johnson |
| Student Records/Registrar Processing Improvements - Fall 2009 | On track | December 31, 2009 | 12/7/2009 - Testing Round 4. | Janice Garcia |
| System Health | On track | August 7, 2009 | 10/30/2009 - 2nd iteration of items in QA | Leema Lallmamode |
| System Health - Network Availability Graphs - Phase II | On track | | 11/20/2009 - Add links for individual buildings. | Mike Brown |
| Timeclock Plus 6.0 | On track | November 30, 2009 | 11/20/2009 - Document Environment Build/Config | Debi Carl |
| Tk20 - Advising and Tracking Tool for CTEL | On track | January 11, 2010 | 12/01/2009 - Complete Requirements for Tk20 Data Pull Queries | Gillian Bailey |
| University Print Management Using Netaphor | On track | December 7, 2009 | | No Project Manager |
| Update CRM Customer Feedback Survey | On track | December 11, 2009 | 12/07/09 - Validate dashboard data | Frank Montoya |
| Upgrade Degree Audit Reporting System (DARS) to u.achieve | On track | July 30, 2010 | 11/30/09 - Request/Setup Web and Database Dev Environments | Barbara Sowden |
| Upgrade Sybase To Version 15.0 | On track | October 13, 2009 | 10/13/2009 - Convert develop2 server to Sybase Version 15 | John Rome (temporarily) |
| USI Server Migration | On track | October 5, 2009 | 1/8/10 -- Target date for ICA migration. | Jane Florez |
| UTO Red Flag Rules Protocol for Identity Theft Prevention Program | On track | November 4, 2009 | 12/9/2009 Project complete and in production | Susan Moore |
| Web Development Standards & Documentation | On track | January 15, 2010 | 11/30/09 - Create Threat Modeling Standard | Barbara Sowden |
| XenApp Version 5.0 Upgrade | On track | January 12, 2010 | November 25, 2009 Windows 2008 image completed. | Sharan Johnson |